Asphalt driveway cost guide
The honest 2026 number is $5–10 per square foot installed. This guide breaks that into line items you can hold a quote against — excavation, base, hot mix, labor and the mobilization fee nobody itemizes.
Contents
Line-item costs
| Item | Unit | Low | High | Average |
|---|---|---|---|---|
| Excavation & grading9–10 in cut; more for soft-spot repair | per ft² | $1 | $3 | $2 |
| Base gravel, delivered6 in compacted needs ~1 ton per 40 ft² | per ton | $18 | $35 | $27 |
| Hot mix asphalt, delivered1 ton ≈ 53 ft² at 3 in compacted | per ton | $100 | $150 | $125 |
| Paving labor + equipmentPaver, rollers, 4–6 person crew | per ft² | $2 | $4 | $3 |
| MobilizationFixed — why small jobs cost more per ft² | per job | $1,500 | $3,000 | $2,250 |
Installed cost by driveway size
| Item | Unit | Low | High | Average |
|---|---|---|---|---|
| Single drive, 12 × 40 ft$7–12/ft² — mobilization dominates | 480 ft² | $3,400 | $5,800 | $4,600 |
| Double drive, 20 × 36 ft$6.50–11/ft² | 720 ft² | $4,600 | $7,900 | $6,250 |
| Long rural drive$5.50–9.50/ft² — scale finally helps | 1,500 ft² | $8,200 | $14,500 | $11,350 |
Comparing against a concrete drive? The concrete cost guide prices the same footprints in concrete — typically 40–60% higher upfront, with the trade-offs covered in the comparison guides below.
Worked budget: a 12 × 40 ft single drive
A straightforward 12 × 40 ft (480 ft²) single driveway on decent soil: 9 in excavation, 6 in compacted base, 3 in hot mix in two lifts. Mid-range unit prices, competitive local market.
- 1
Excavation & grading at $1.75/ft²
480 × $1.75 = $840
- 2
Base gravel: 6 in over 480 ft² ≈ 15 tons compacted, at $28/ton
15 × $28 = $420
- 3
Hot mix: 480 ÷ 53 ≈ 9.1 tons, +10% waste → 10 tons at $120
10 × $120 = $1,200
- 4
Paving labor + equipment at $2.60/ft²
480 × $2.60 = $1,250
- 5
Mobilization share (small-job rate)
$800 (bundled with two nearby jobs)
Result: Total ≈ $4,510 — about $9.40/ft², squarely inside the $3,400–5,800 range for this size. A standalone mobilization at $2,000+ pushes the same job past $5,700.
Where the money actually goes
Two-thirds of the budget is not asphalt. That is why haggling over the hot mix price moves a quote very little, while job access, excavation surprises and crew efficiency move it a lot — and why the cheapest quote usually got cheap by thinning the parts you cannot see.
Cost questions
Run the full material budget
The asphalt cost calculator turns area, thickness and your local per-ton price into a complete material estimate.