Skip to content
MaterialsCalc
Concrete · Walls

Concrete Wall Calculator

Length × height × thickness, minus openings, plus the right waste factor. The notes below cover the part calculators can't do: getting the concrete into the form safely.

1 yd³
per 40 ft² of 8 in wall
4–5 ft/hr
safe pour rate @ 70°F
5–6 in
target slump for walls
2 sides
of formwork required

Concrete Wall Calculator

Cast-in-place walls: foundations, retaining walls, stem walls. Subtracts window and door openings.

Windows, doors, beam pockets. Leave 0 for a solid wall.

Quick answer

How much concrete do I need for a foundation wall?

A 20 ft run of 8-inch foundation wall, 8 ft high, needs about 4.35 yd³ of concrete with a 10% waste allowance — roughly 8 tonnes. Openings like windows and doors subtract directly from this volume before the waste factor is applied.

Rule of thumb:
An 8-inch wall uses about 1 cubic yard per 40 ft² of wall face, before waste.
Formula:
Order (yd³) = ((Run × Height − Openings) × Thickness ÷ 27) × (1 + waste)

Walls by common run length

8 in thick, 8 ft high, no openings, 10% waste included. Cost uses the $150–180/yd³ delivered ready-mix range from our concrete cost guide.
Wall run (8 in × 8 ft high)Order (yd³)Approx. weightEst. material cost
20 ft4.35 yd³8.0 t$653–783
40 ft8.69 yd³16.0 t$1,304–1,564
60 ft13.04 yd³23.9 t$1,956–2,347
80 ft17.38 yd³31.9 t$2,607–3,128
100 ft21.73 yd³39.9 t$3,260–3,911

Wall volume math, with openings

Formula

V = (L × H − A₀) × t × (1 + waste)

L
wall length (ft or m)
H
wall height (ft or m)
A₀
total area of openings (ft² or m²)
t
wall thickness (ft or m)

Corners are counted once: measure lengths along the wall centerline, or measure outside faces and accept ~1% overage on a rectangular foundation.

For a full foundation, run each wall face through the calculator (or sum the centerline perimeter and treat it as one long wall). Remember the footing below is a separate volume — the footing calculator handles that, and the two pours are usually days apart anyway.

Worked example: basement with a walkout

Worked example

A 36 × 28 ft basement, 8 ft walls, 8 in thick. One walkout door (7 × 4 ft) and four window bucks (each 32 × 16 in).

  1. 1

    Centerline perimeter

    2 × (36 + 28) = 128 ft

  2. 2

    Gross wall face

    128 × 8 = 1,024 ft²

  3. 3

    Openings

    28 ft² (door) + 4 × 3.6 ft² = 42.2 ft²

  4. 4

    Net face × thickness

    (1,024 − 42.2) × 0.667 = 654.8 ft³

  5. 5

    Add 10%, convert to yards

    654.8 × 1.10 ÷ 27 = 26.7 yd³

Result: Order 27 yd³ — that's three 9-yard trucks, so sequence them 45 minutes apart.

Formwork pressure: the safety constraint

Concrete per square foot of wall

Yards per 100 ft² of wall face — memorize your thickness and you can estimate standing in the excavation.

Concrete per 100 ft² of wall face

Wall pour questions

How much concrete is in an 8-inch foundation wall?
An 8 in wall holds 0.667 ft³ per square foot of wall face — almost exactly 1 yd³ per 40 ft² of wall. A typical 8 ft tall, 40 ft long wall face (320 ft²) therefore needs about 8 yd³ before waste.
Should I subtract window and door openings?
Yes, when they're large. A single basement window buck (say 32 × 16 in ≈ 3.5 ft²) is noise inside the waste allowance, but a walkout door plus three windows in one wall can exceed 60 ft² — nearly 1.5 yd³ in an 8 in wall. The calculator's openings field handles this.
How fast can I fill a wall form?
Form pressure is governed by pour rate and concrete temperature (ACI 347). Standard residential panel forms are commonly rated around 600–800 psf, which at 70°F works out to roughly 4–5 ft of placement per hour. Filling a full-height 8 ft wall in one fast pass can blow out forms — pour in lifts around the wall instead.
What slump should wall concrete be?
5–6 in slump places well in walls; anything stiffer honeycombs around rebar and anything wetter is usually water added on site, which cuts strength (each added gallon per yard costs roughly 200 psi). Order a mid-range water-reducer mix rather than adding water at the truck.
Is an ICF wall calculated the same way?
The concrete core is — length × height × core thickness (typically 6 or 8 in) minus openings. The foam form adds no concrete. ICF suppliers publish per-form volumes; they agree with this calculator to within a percent or two.

Compare your wall estimate against ready-mix pricing in the cost guide

Related calculators & guides

Sources & references

  1. [1]ACI 347R-14: Guide to Formwork for Concrete — American Concrete Institute, 2014
  2. [2]ASTM C94/C94M: Standard Specification for Ready-Mixed Concrete — ASTM International, 2024
  3. [3]ACI 318-19: Building Code Requirements for Structural Concrete — American Concrete Institute, 2019